23/02173/DISC_A | DISCHARGE OF CONDITION 6 AND 7 OF PLANNING CONSENT - 23/02173/FM - New Warehouse | Ravago Building Solutions UK Ltd Estuary Road King's Lynn Norfolk PE30 2HJ Discharge of Condition final letter
  • Print summary icon
Received
Thu 02 May 2024
Validated
Mon 13 May 2024
Consultation
Wed 12 Jun 2024
Recommendation and/or Committee
Decided
Wed 24 Jul 2024
  • Total Consulted: 7
  • Consultees Responded: 6
  • View all comments icon

Search Filters

Collapse All|Expand All

Norfolk Historic Environment Service

Consultation Date: Mon 13 May 2024

Local Lead Flood Authority Norfolk County Council

Consultation Date: Wed 22 May 2024

Anglian Water Services Ltd

Consultation Date: Wed 22 May 2024

Water Management Alliance

Consultation Date: Mon 13 May 2024

Environment Agency

Consultation Date: Wed 15 May 2024

Clancy Consulting

Comment Date: Wed 22 May 2024

Further information and details are required to demonstrate that a sustainable surface water drainage strategy has been considered and can be achieved prior to discharge of surface water planning conditions which accords with the principles set out in Development Management Policy DM4.2, the LLFA, Statutory Consultee for Planning ' Guidance Document V6.1, the Non-Statutory Technical Standards for Sustainable Drainage Systems and the SuDs Manual (CIRIA C753 - 2015). https://www.gov.uk/government/publications/sustainable-drainage-systems-non-statutory-technical-standards

The submitted information should include:

Details confirming that the surface water drainage hierarchy has been followed with all available options being considered, with a preference for shallow infiltration features below 2m deep followed by discharge to local watercourses. If these options are unfeasible then discharge to surface water sewer will be considered. The last method is discharge is to a combined sewer, or via deep infiltration features (those in excess of 2m.) Discharge of surface water to a foul sewer is not acceptable.

A Ground Investigation Report must be provided if relying on infiltration showing that infiltration testing has been carried out to BRE 365 along with evidence that seasonally high ground water levels are 1.2m below the base of any proposed infiltration structure.

If the site proposals include discharge to a ditch/watercourse or culverted watercourse, evidence is required confirming that the watercourse/culvet is capable of accepting the flows from the development which should be limited to peak greenfield rate for the 1 in 100 year rainfall event with allowance for climate change unless otherwise agreed with the appropriate Internal Drainage Board (IDB).

New development proposals should include hydraulic calculations based on greenfield discharge rates for discharge to watercourses or infiltration rates found in the Ground Investigation Report if utilising infiltration.

Where developing a brownfield site betterment of surface water runoff must be considered. Brownfield surface water runoff rates and volumes should be attenuated as close to greenfield rates as possible.

Calculations should be based on FEH rainfall data and should take account of the governments updated guidance on climate change allowances for peak rainfall intensity demonstrating that the 20% and 40% climate change scenarios have been tested to ensure no flooding of buildings. https://www.gov.uk/guidance/flood-risk-assessments-climate-change-allowances

Consideration of how flows on the site exceeding the 1% plus 40% climate change rainfall event and plan or commentary on how finished ground floor levels may assist with minimising impacts.

Maintenance program / schedule and on-going maintenance responsibilities of each part of the drainage infrastructure and where appropriate watercourses / culverts (including clear distinction between private / IDB / LLFA / Anglian Water).

Details will also be required of any riparian ownership responsibilities, including access arrangements for maintenance, which should be incorporated into the maintenance and management plan for the proposed development, to ensure future maintenance responsibilities are identified and understood. Details of Riparian ownership and responsibilities can be found at; https://www.norfolk.gov.uk/rubbish-recycling-and-planning/flood-and-water-management/information-for-homeowners/living-next-to-a-watercourse

Any proposed new culverts or works affecting the flow of a watercourse requires the prior written consent of the Lead Local Flood Authority (Norfolk County Council) or relevant IDB where watercourses are maintained and managed by them under the terms of the Land Drainage Act 1991 (as amended by the Flood & Water Management Act 2010)/Water Resources Act 1991.

The Lead Local Flood Authority seeks to avoid the use of culverts and consent for such works will not normally be granted, except as a means of access. It should be noted that this consent is required in addition to any planning permission granted. Further information can be found at; https://www.norfolk.gov.uk/rubbish-recycling-and-planning/flood-and-water-management/information-for-homeowners/consent-for-work-on-ordinary-watercourses

Community Safety And Neighbourhood Nuisance

Comment Date: Wed 22 May 2024

I have assessed this application in relation to condition 6 and can confirm that as the agent has stated in an email dated 13 May 2024 that there is no foul water for this building, I have no comments to make.