Planning – Application Comments

Help with this page (opens in a new window)

25/00692/DISC_C | DISCHARGE OF CONDITIONS 3 AND 9 ATTACHED TO PLANNING PERMISSION 25/00692/F - Removal of the existing car wash and jet wash, erection of a single storey extension to the existing petrol filling stations sales building, raising the height of the PFS canopy and the creation of an electric vehicle charging zone, jet wash facilities, substation, LV panel, bin store and associated works | MORRISONS Service Station 40 Elm High Road Emneth Wisbech Norfolk PE14 0DQ Discharge of Condition final letter
  • Print summary icon
Received
Mon 23 Mar 2026
Validated
Tue 24 Mar 2026
Consultation
Tue 14 Apr 2026
Recommendation and/or Committee
Decided
Wed 13 May 2026
  • Total Consulted: 5
  • Consultees Responded: 3
  • View all comments icon

Search Filters

Collapse All|Expand All

Anglian Water Services Ltd

Consultation Date: Tue 24 Mar 2026

Middle Level Commissioners Inc

Consultation Date: Tue 24 Mar 2026

Clare Harpham

Comment Date: Tue 14 Apr 2026

Condition 3 - External lighting

In line with the comments made by CSNN , this condition cannot be discharged at this time

Condition 6 - Foul and Surface Water Drainage

In line with the comments made by Anglian Water and Flood and Civil consultants, this condition cannot be discharged at this time

Condition 9 - Noise Management

In line with the comments made by CSNN , this condition cannot be discharged at this time

Flood And Civil Ltd - Foul Water Only

Comment Date: Thu 14 May 2026

Thank you for your submission. We have the following comments:

' Because the proposal relies on the performance of the existing system, the applicant should provide evidence of exceedance routing in the event the receiving system fails due to blockage or lacks capacity during extreme events. The applicant should provide a plan showing exceedance flow routes, stored flood volumes and any flood risk mitigation. Should include external levels and finished floor levels of buildings.

' A SuDS Water Quality Assessment is required. While the drawing refers to two new gullies and retention of the existing petrol interceptor, further details are required to demonstrate how runoff from the new gullies will be treated, whether it passes through the existing interceptor, and whether that interceptor has adequate capacity and remains in suitable working order. We would also encourage the applicant to explore the use of a green roof on the extension as a proportionate way of improving water quality and wider SuDS benefits.

' Agreement in principle for discharge to the existing sewer network (indirectly) with the sewer undertaker.

' Management and maintenance plan identifying the future maintenance requirements and which body/bodies will own and be responsible for maintenance of the system and how they will be funded, for the lifetime of the development.

' Details of how the drainage system will be protected during construction and how runoff (including any pollutants) from the development site will be managed before the drainage system is operational.

Community Safety And Neighbourhood Nuisance

Comment Date: Fri 27 Mar 2026

I confirm that I have no objection to conditions 3 and 9 being discharged

Powered by Idox