Planning – Application Dates

Help with this page (opens in a new window)

10/00883/DISC_E | DISCHARGE OF CONDITION 25 ATTACHED TO PLANNING PERMISSION 10/00883/FM: A wind energy development comprising the erection and 25 year operation of five wind turbines with a maximum blade height of 100m and up to 50m -micrositing, together with ancillary infrastructure including on-site access tracks, hard standing areas, control buildings and cabling and a permanent anemometer mast | Land Between Bagthorpe Barner And Syderstone Known As Chiplow Main Road Bagthorpe Norfolk Discharge of Condition final letter
  • Print summary icon
Received
Fri 12 Sep 2014
Validated
Mon 15 Sep 2014
Consultation
Tue 07 Oct 2014
Recommendation and/or Committee
Decided
Tue 13 Jan 2015
Application Received Date Fri 12 Sep 2014
Application Validated Date Mon 15 Sep 2014
Expiry Date Fri 10 Oct 2014
Actual Committee Date
Latest Neighbour Consultation Date
Neighbour Consultation Expiry Date
Standard Consultation Date Tue 16 Sep 2014
Standard Consultation Expiry Date Tue 07 Oct 2014
Last Advertised In Press Date
Latest Advertisement Expiry Date
Last Site Notice Posted Date
Latest Site Notice Expiry Date
Internal Target Date Mon 10 Nov 2014
Agreed Expiry Date
Decision Made Date Tue 13 Jan 2015
Decision Issued Date Tue 13 Jan 2015
Permission Expiry Date
Decision Printed Date
Environmental Impact Assessment Received
Determination Deadline Mon 10 Nov 2014
Temporary Permission Expiry Date