19/00456/F
|
Variation of condition 13 of Planning Permission 18/01864/FM: Erection of anaerobic digestion facility to process biomass including reception/office building and workshop, digesters, storage tanks, combined heat and power plant, energy crop storage area, and ancillary plant.
|
Land N of Outfall S Off Transmission Cables W Off Road Cross Bank Road King's Lynn Norfolk
Application Permitted
Received
Wed 13 Mar 2019
Validated
Wed 13 Mar 2019
Consultation
Thu 04 Apr 2019
Recommendation and/or Committee
Decided
Thu 02 May 2019
| Application Received Date | Wed 13 Mar 2019 |
|---|---|
| Application Validated Date | Wed 13 Mar 2019 |
| Expiry Date | Thu 11 Apr 2019 |
| Actual Committee Date | |
| Latest Neighbour Consultation Date | Thu 14 Mar 2019 |
| Neighbour Consultation Expiry Date | Thu 04 Apr 2019 |
| Standard Consultation Date | Thu 14 Mar 2019 |
| Standard Consultation Expiry Date | Thu 04 Apr 2019 |
| Last Advertised In Press Date | |
| Latest Advertisement Expiry Date | |
| Last Site Notice Posted Date | Thu 14 Mar 2019 |
| Latest Site Notice Expiry Date | Thu 11 Apr 2019 |
| Internal Target Date | Wed 08 May 2019 |
| Agreed Expiry Date | |
| Decision Made Date | Thu 02 May 2019 |
| Decision Issued Date | Thu 02 May 2019 |
| Permission Expiry Date | Mon 02 May 2022 |
| Decision Printed Date | |
| Environmental Impact Assessment Received | |
| Determination Deadline | Wed 08 May 2019 |