19/00456/F | Variation of condition 13 of Planning Permission 18/01864/FM: Erection of anaerobic digestion facility to process biomass including reception/office building and workshop, digesters, storage tanks, combined heat and power plant, energy crop storage area, and ancillary plant. | Land N of Outfall S Off Transmission Cables W Off Road Cross Bank Road King's Lynn Norfolk Application Permitted
  • Print summary icon
Received
Wed 13 Mar 2019
Validated
Wed 13 Mar 2019
Consultation
Thu 04 Apr 2019
Recommendation and/or Committee
Decided
Thu 02 May 2019
Application Received Date Wed 13 Mar 2019
Application Validated Date Wed 13 Mar 2019
Expiry Date Thu 11 Apr 2019
Actual Committee Date
Latest Neighbour Consultation Date Thu 14 Mar 2019
Neighbour Consultation Expiry Date Thu 04 Apr 2019
Standard Consultation Date Thu 14 Mar 2019
Standard Consultation Expiry Date Thu 04 Apr 2019
Last Advertised In Press Date
Latest Advertisement Expiry Date
Last Site Notice Posted Date Thu 14 Mar 2019
Latest Site Notice Expiry Date Thu 11 Apr 2019
Internal Target Date Wed 08 May 2019
Agreed Expiry Date
Decision Made Date Thu 02 May 2019
Decision Issued Date Thu 02 May 2019
Permission Expiry Date Mon 02 May 2022
Decision Printed Date
Environmental Impact Assessment Received
Determination Deadline Wed 08 May 2019
Temporary Permission Expiry Date